Greenstone Mine Project
Inspection Summary
Document reference number: 64
Project Name: Greenstone Gold Mine
Proponent Name: Greenstone Gold Mines
Inspection Date: June 06, 2023
Project Description:
Greenstone Gold Mines will be carrying out the construction, operation, decommissioning and abandonment of an open-pit gold mine and on-site metal mill located approximately five kilometers south of Geraldton, Ontario, at the intersection of Highway 11 (Trans-Canada Highway) and Michael Power Boulevard. As proposed, the gold mine would have an ore production capacity of 30,000 tons per day, and the metal mill would have an ore input capacity of 30,000 tons per day.
Link to Decision Statement: 139551E.pdf (iaac-aeic.gc.ca)
Enforcement officers designated under the Impact Assessment Act (IAA) conducted a site inspection of the Greenstone Gold Mine on June 06, 2023. The project is in the construction phase.
The enforcement officers inspected the following conditions:
- Condition # 3 - Fish and Fish Habitat
- Condition # 5 - Health and socio-economic conditions of Indigenous Peoples
- Condition # 9 - Accidents and Malfunctions
If you have questions or comments relating to the Agency's Enforcement Operations Team or the Agency's enforcement activities, you may contact enforcement-applicationdelaloi@iaac-aeic.gc.ca.